WO-2026-0032 · Gross Motor Play Gym — 4 Piece – Birch Demo Assembly · batch B-260172
xero synced 9:14 am 17 Aug 2026

WO-2026-0032

Complete Assembly

13 × Gross Motor Play Gym — 4 Piece – Birch · replenishment for the shelf

← Board
Planned Cut & machined On the bench Finishing Complete Due 15 Sep 2026
Pick list — 13 off the bill of material
Every quantity here is the bill multiplied out. Running the build takes them out of stock.
CodeMaterialRequired IssuedOn hand Unit costLine cost
MAT-BP18-BB Birch plywood 2440×1220 × 18mm BB/BB 32.5 sheet 32.5 166 $218.50 $7,101.25
MAT-BP12-BB Birch plywood 2440×1220 × 12mm BB/BB 14.3 sheet 14.3 15 $152.00 $2,173.60
MAT-BP06-BB Birch plywood 2440×1220 × 6mm BB/BB 11.7 sheet 11.7 9 $86.00 $1,006.20
MAT-BIR-EDG Birch edging tape 22mm, per lineal m 416 lm 416 2,011 $2.95 $1,227.20
FIN-OIL-CL Hardwax oil, clear, low-tox — per litre 10.27 L 10.27 79.43 $62.50 $641.88
FIN-SAND-120 Abrasive belt 120 grit 17.55 ea 17.55 29 $8.90 $156.20
HW-CONF-50 Confirmat screw 7×50 182 ea 182 12,195 $0.18 $32.76
HW-GLIDE Felt glide, screw-in 78 ea 78 644 $0.95 $74.10
PKG-CTN-L Carton, large, double wall 13 ea 13 754 $7.20 $93.60
PKG-CORNER Corner board, per lineal m 117 lm 117 1,362 $0.85 $99.45
Materials $12,606.23
Bench time booked
Each booking costs at the rate of the bench that did the work — CNC is dearer than sanding
WhenWhoBenchAt stageMinutesRate / hCost
06 Aug 2026, 7:50 am Raj Patel Finishing Finishing 1,150 $98.00 $1,878.33
07 Aug 2026, 7:15 am Jess Mattingly CNC Router Cut & machined 1,976 $115.00 $3,787.33
07 Aug 2026, 10:00 am Pete Rasmussen Edging Cut & machined 973 $88.00 $1,427.07
10 Aug 2026, 7:15 am Dave Kuiper Assembly On the bench 1,602 $94.00 $2,509.80
12 Aug 2026, 8:15 am Anahera Wilson Sanding On the bench 953 $82.00 $1,302.43
Total 6,654 $10,904.96
What this actually costs to make
Materials plus the bench time, per unit
$1,808.55
each, over 13 in this batch
Materials
$12,606.23
Booked labour
$10,904.96
Batch cost
$23,511.19
List price each $1,765.00
Margin each -$43.55 · -2%

The materials half comes off the bill on its own. The labour half only exists because the time is booked against the job as it moves — without it, the cost of a piece is the plywood and nothing else.

Where the time went
CNC Router 32 h 56 min $3,787.33
Assembly 26 h 42 min $2,509.80
Finishing 19 h 10 min $1,878.33
Edging 16 h 13 min $1,427.07
Sanding 15 h 53 min $1,302.43
Job details
Making
52261-11 Birch
Batch
B-260172
Raised
17 Aug 2026
Due
15 Sep 2026
Completed
10 Aug 2026
Planned time
117 h
Booked time
110 h 54 min -5%
Owner
Dave Kuiper