WO-2026-0015 · Rise Up Desk — Non-Tilting – Oak Demo Assembly · batch B-260155
xero synced 9:14 am 17 Aug 2026

WO-2026-0015

Cut & machined Assembly

11 × Rise Up Desk — Non-Tilting – Oak · for SO-2026-0396 (Kadimah School)

← Board
Planned Cut & machined On the bench Finishing Complete Due 09 Sep 2026 · in 23 days
Pick list — 11 off the bill of material
Every quantity here is the bill multiplied out. Running the build takes them out of stock.
CodeMaterialRequired IssuedOn hand Unit costLine cost
MAT-BP18-BB Birch plywood 2440×1220 × 18mm BB/BB 11 sheet 11 166 $218.50 $2,403.50
MAT-BP12-BB Birch plywood 2440×1220 × 12mm BB/BB 4.4 sheet 4.4 15 $152.00 $668.80
MAT-OAK-EDG Oak edging tape 22mm, per lineal m 143 lm 143 2,165 $3.40 $486.20
MAT-OAK-VEN European oak veneer, 0.6mm, per m² 17.6 m2 17.6 315 $38.50 $677.60
FIN-OIL-CL Hardwax oil, clear, low-tox — per litre 3.41 L 3.41 79.43 $62.50 $213.13
FIN-SAND-120 Abrasive belt 120 grit 5.94 ea 5.94 29 $8.90 $52.87
HW-CONF-50 Confirmat screw 7×50 132 ea 132 12,195 $0.18 $23.76
HW-GAS-STY Gas stay, 60N 22 ea 22 159 $18.40 $404.80
HW-GLIDE Felt glide, screw-in 88 ea 88 644 $0.95 $83.60
PKG-CTN-M Carton, medium, double wall 11 ea 11 1,057 $4.80 $52.80
PKG-CORNER Corner board, per lineal m 44 lm 44 1,362 $0.85 $37.40
Materials $5,104.45
Bench time booked
Each booking costs at the rate of the bench that did the work — CNC is dearer than sanding
WhenWhoBenchAt stageMinutesRate / hCost
10 Aug 2026, 8:20 am Pete Rasmussen Edging Cut & machined 284 $88.00 $416.53
10 Aug 2026, 1:40 pm Wiremu Ngata CNC Router Cut & machined 616 $115.00 $1,180.67
Total 900 $1,597.20
What this actually costs to make
Materials plus the bench time, per unit
$609.24
each, over 11 in this batch
Materials
$5,104.45
Booked labour
$1,597.20
Batch cost
$6,701.65
List price each $710.00
Margin each $100.76 · 14%

The materials half comes off the bill on its own. The labour half only exists because the time is booked against the job as it moves — without it, the cost of a piece is the plywood and nothing else.

Where the time went
CNC Router 10 h 16 min $1,180.67
Edging 4 h 44 min $416.53
Job details
Making
51721-12 Oak
Batch
B-260155
Raised
10 Aug 2026
Due
09 Sep 2026
Planned time
39 h 25 min
Booked time
15 h -62%
Owner
Dave Kuiper